PSE will be installing new underground electrical cables under Marigold Drive starting Monday, August 26th, 2019. During the installation process, the west/outbound lane of Marigold Drive between Clubhouse Circle and the entrance to Sun Mark Realty will be closed to through traffic. Flaggers will provide traffic control for vehicle use of the eastbound lane of Marigold Drive. As part of this construction project, work will also occur in the Center Condominiums’ parking lot. Flyers will be placed on the doors of all Center Condo units explaining parking options.

Construction Schedule:

Monday, August 26th: The westbound lane on Marigold will be closed for underground directional drilling.

Tuesday, August 27th: The westbound lane on Marigold will be closed to cut a trench across the road and into the Center Condominiums.

Wednesday, August 28th: Closed, Center Condo’s Marigold Drive entrance for underground directional drilling through the Center Condo parking lot.

Thursday, August 29th: All of the parking spaces in front of the Center Condos will be closed to allow asphalt cutting and trenching.

Tuesday, September 3rd: All of the parking spaces in front of Center Condos will be closed to allow underground directional drilling from the parking lot to the Spa.