Due to the high volume of tree debris in Gates 3, 9, & 13, Maintenance is a few days behind schedule. The week of May 12th Maintenance will be working in Gate 1, as well as working to complete Gates 3, 9, & 13.
2025 Firewise schedule:
- Gate 5 (Maintenance Zones 51, 52, 53) – COMPLETE
- Gate 3 (Maintenance Zones 3, 4, 5, 6) – In Progress
- Gates 9 & 13 (Maintenance Zones 1, 2) – In Progress
- Gate 1 (Maintenance Zones 10, 11, 12, 14, 15) – Set out debris by May 12
- Gate 2 (Maintenance Zones 20, 21, 22, 23, 24, 25, 26) – Set out debris by May 19
Pickup for each gate will take place over the course of a week starting on the above dates.