2017 Roads Maintenance Schedule

2017 Roads Work Starts August 8th

The Finance Committee and Board of Directors unanimously voted to authorize an allocation not to exceed $464,345 from the Roads Capital account to fund the 2017 Roads Work.

Three contractors (Granite Construction, Colacurcio Brothers and Faber Construction) all submitted fully compliant bids against our requirements with Granite Construction’s bid evaluated as both best value and lowest bid. 

(Click) Bid Specifications       (Click) Bid Proposal – Summary Sheet

Granite Construction is a well-respected company with substantial experience on similar projects. They have been in business since 1922 and have a significant local presence in Whatcom County which includes a materials plant.

Granite Construction was awarded the bid and is now gearing up to start work.  Work is expected to start August 14th and complete by September 8th

1 Morning Glory Drive–Reconstruction:  mill and repave
2 Sudden Valley Drive–mill and repave delamination
3 Gate 9–mill and repave delamination
4 Tumbling Water Drive — Reconstruction:  mill and repave
5 Sunflower Circle — Pothole repair; reconstruction
A Multiple Locations: all gates –Crack Sealing
A Multiple Locations: all gates–Pothole Repair
A Main & Secondary Roads–Striping: Centerlines and fog lines

Sudden Valley staff will place signs in neighborhoods in advance of the work being started. The construction schedule or map showing the location of work (items 1, 2, 3, 4and 5) can be viewed on our SVCA WEB site under the 2017 Roads Maintenance tab.

Please contact the General Manager, Mitch Waterman, at GM@suddenvalley.com if you have questions, comments or concerns.